Version 6 (modified by lhella, 10 years ago)

--

Procedure for Maintenance of PCA Reference Data Library

Status of this document: Working draft

Contents

  1. Abstract
  2. Project Objective
  3. Proposed Scope
  4. Procedural steps, actions, time-frame and responsibility
    1. Initiation of Change Request
    2. Preparation for evaluation
    3. Evaluation of the Change Request
    4. Preparation for validation
    5. Validation of the Change Request
    6. Resolution of the CR
    7. Implementation of CR
  5. Definition and clarification of terms
    1. Terms for general use
    2. Terms for Status Identification of Change Requests (CR)
    3. Terms for Status Identification of Database Items (DI)

Abstract

This document contains an a procedure by which POSC Caesar Association (PCA) shall maintain and update the PCA Reference Data Library (PCA RDL), based on ISO 15926 and hosted by PCA Reference Data Services (PCA RDS).

Project Objective

The goal of this procedure is to describe the criteria and activities required to be performed by the various PCA Special Interest Groups (SIG), in order to add, modify and delete Reference Data from the parts of the PCA RDL for which they have been assigned responsibility.

Proposed Scope

The procedure is based on ISO Annex ST "Procedure for the development and maintenance of standards in database format." However, it is limited to maintenance of existing standard items (and does not include development of new standards, nor review and withdrawal of existing standards).

Furthermore, the procedure only deals with maintenance action following the so-called "normal database procedure" which makes use of a Validation Team and a workflow around a dataset for information sharing; and is used by ISO for validation of new items or item combinations that are within the boundary of existing rules.

This excludes actions according to the ISO "original procedure" relying on circulation of documents with standardized content to the National Bodies (i.e., to the PCA member companies in the case of the PCA RDL). It also excludes actions according to the ISO "Extended database procedure" which has the same stages and time frames as the "original procedure" but is implemented as a workflow around a database.

Procedural steps, actions, time-frame and responsibility

The procedure is described in a summary fashion, highlighting the action(s) that are required on each step, as well as the required time-frame and associated responsibility.

The sections following subsections describe the various steps associated with the process for proposed maintenance of the PCA RDL.

Initiation of Change Request

When a Change request (CR) is received from a Proposer in an RD Update File with the specified RD Input Format, the submitted CR is entered into the PCA RDL Request Log with status identifier "submitted" and the Proposer is automatically notified. The Proposer needs to be a registered user and submit the CR to the RDS Operations Support Ticket system. The Proposer must be clearly identified, and can e.g. be an individual, a project, a company. If the Proposer is a group, a main person of contact should be identified (by name and email address).

The CR shall consist of the following:

All CR that contain extensions to the PCA RDL must :

Preparation for evaluation

The CR is checked for completeness and consistency by the PCA RD Maintenance Team staff. This includes ensuring that all mandatory administrative and meta-data entries are appropriately filled-in and that any necessary accompanying items are of a quality sufficient for evaluation. This check is fully automated.

-> obs sufficient quality? sjekkes det her? da er det automatisk + manuelt?

If this initial check is satisfactory the CR is given status identifier "for evaluation" and the Proposer is notified about the status update. When a CR has passed this initial check, the content will be uploaded to the PCA Development endpoint. If the CR is deemed not to be satisfactory, the Proposer is notified with the reason(s) for rejection. This shall take place within a maximum of 5 (five) working days after receiving the CR (after the status identifier was set to "submitted").

Evaluation of the Change Request

If the quality of the information in the Work Package (CR) is satisfactory, the PCA RD Maintenance Team Staff sets the status of the Change Request to "for validation" and notifies the Proposer about status update. If the CR is deemed not to be satisfactory, the Proposer is notified with the reason(s) for rejection. Notification shall take place within 5 (five) working days after initial acceptance of the CR (after the status identifier was set to "for evaluation").

If considered practical, the PCA RD Maintenance Team Staff may decide to combine items under more than one CR into one Work Package, or to separate items submitted under one CR into several Work Packages, in order to assign relevant parts of the CR (database items) to (one or more) relevant PCA SIGs.

Preparation for validation

The PCA SIG Validation Team Responsible determines whether the Change Request (Work Package) is within the scope of the PCA RDL and valid for evaluation (or should be rejected),

Notification shall be sent to the PCA RD Maintenance Team within 5 (five) working days after receiving the Work Package (10 working days after the status identifier was set to "for validation").

Validation of the Change Request

For the validation to be satisfactory (valid) more than half (a simple majority) of the PCA SIG Validation Team members must approve the proposed updates. If the Proposer of a CR is a SIG, then a team for validation must be assigned by the PCA TAB. The team must consist of domain experts that has been part of developing the CR, external domain experts and ISO 15926 experts.

This must be completed within a maximum of 30 (thirty) working days after the PCA SIG Validation Team sends its decision about the Work Package (CR) back to the PCA RD Maintenance Team.

Resolution of the CR

Given evaluation of the PCA SIG Validation team, the Work Package may be

  • approved for inclusion in the PCA RDL and uploaded to the PCA staging area
  • sent back to the Proposer with requests for modification
  • sent back to the Proposer with requests for modification and resubmittal
  • rejected

The decision of the PCA SIG Validation Team is communicated back to the PCA RD Maintenance Team within five (5) working days after the necessary number of members has completed their validation.

Implementation of CR

After a CR is approved (either directly or after required modification), the PCA RD Maintenance Team staff uploads/changes any required in the PCA RDL, sets the status identification to "resolved" and notifies the Proposer about planned inclusion of CR to the production endpoint. This shall take place within 10 (ten) working days receiving the decision of acceptance by the PCA SIG Validation was received by the PCA RD Maintenance Team

Thus the maximum total time from receiving an initial Change Request to Implementation (given that everything is accepted on first pass) shall be 60 (sixty) working days.

The note should probably continue the process description with description of tasks for normal database procedure. This is not required for PCA RD Maintenance procedure, but important for presentation of procedure to ISO.

Definition and clarification of terms

Add definition of terms by modifying definitions in ISO ST_DBS N52 (Rev 1)

Terms for general use

  • PCA
  • PCA RDS
  • PCA RDL
  • PCA RDL Request Log
  • PCA RDL Update File
  • PCA RDL Input Format
  • PCA RD Maintenance Team
  • PCA SIG RD Validation Team
  • PCA SIG Responsible -> refereres ikke til noe sted
  • Proposer
  • Change Request (CR)
  • Work Package
  • Original Procedure
  • Normal database procedure
  • Extended database procedure
  • Database standard
  • Item (of a database standard)

Terms for Status Identification of Change Requests (CR)

  • Submitted
  • For Evaluation
  • For Validation
  • Resolved

These statuses are reflected by the Ticket system, and will be used by RDS Operations to indicate where the CR is in the process.

Terms for Status Identification of Database Items (DI)

  • Proposed
  • Draft
  • Released
  • To be revised
  • Confirmed
  • Withdrawn
  • Rejected