| 8 | = Current IOHN budget allocation = |
| 9 | |
| 10 | Accepted at SC meeting No 5, dated March 25th, 2009. |
| 11 | |
| 12 | ||'''Activity'''||'''Budget (NOK)'''|| |
| 13 | ||1. Robust sensor networks||--- (on hold)|| |
| 14 | ||2. Infrastructure and service platform||6 770 000|| |
| 15 | ||3. Semantic platform and information validation||21 250 000|| |
| 16 | ||4. Risk management for reliable information & IT||21 960 000|| |
| 17 | ||5. Unmanned drilling rig||15 300 000|| |
| 18 | ||6. Improved production||5 750 000|| |
| 19 | ||7. Sub-ice operation||4 700 000|| |
| 20 | ||Management||9 000 000|| |
| 21 | ||Dissemination||1 490 000|| |
| 22 | ||Contingency||4 700 000|| |
| 23 | ||'''Total'''||'''89 540 000''|| |
| 24 | |
| 25 | Note: 799 647,- from Contingency to cover start-up costs DNV (pre May 1, 2008). |