Current IOHN budget allocation
Accepted at SC meeting No 5, dated March 25th, 2009.
Activity | Budget (NOK) |
1. Robust sensor networks (on hold) | --- |
2. Infrastructure and service platform | 6 770 000 |
3. Semantic platform and information validation | 21 250 000 |
4. Risk management for reliable information & IT | 21 960 000 |
5. Unmanned drilling rig | 15 300 000 |
6. Improved production | 5 750 000 |
7. Sub-ice operation | 4 700 000 |
Management | 9 000 000 |
Dissemination | 1 490 000 |
Contingency | 4 700 000 |
Total | 89 540 000 |
Note: 799 647,- from Contingency to cover start-up costs DNV (pre May 1, 2008).